Scheers Specializing in Bonds Since 1963
Home Builders and Developers
Vortex 1
General and Trade Contractors
Vortex 2
Environmental Companies
Vortex 3
Manufacturing Companies
Latge Vortex
 
    

Status of Outstanding Contracts

download Acrobat pdf

Name of Contractor: *
Address: *
City: *
State: *
Zip: *
Uncompleted Contracts As of: *
 
1. Contract Description and Location: *
Contract Price Including Approved Change Orders: *
Contractor's Estimated Cost at Time of Bid (1): *
Total Amount Billed to Date Including Retainage (2): *
Total Costs To Date: *
Total Revised Estimated Costs to Complete (3): *
Estimated Completion Date: *
 
2. Contract Description and Location:
Contract Price Including Approved Change Orders:
Contractor's Estimated Cost at Time of Bid (1):
Total Amount Billed to Date Including Retainage (2):
Total Costs To Date:
Total Revised Estimated Costs to Complete (3):
Estimated Completion Date:
 
3. Contract Description and Location:
Contract Price Including Approved Change Orders:
Contractor's Estimated Cost at Time of Bid (1):
Total Amount Billed to Date Including Retainage (2):
Total Costs To Date:
Total Revised Estimated Costs to Complete (3):
Estimated Completion Date:
 
4. Contract Description and Location:
Contract Price Including Approved Change Orders:
Contractor's Estimated Cost at Time of Bid (1):
Total Amount Billed to Date Including Retainage (2):
Total Costs To Date:
Total Revised Estimated Costs to Complete (3):
Estimated Completion Date:
 
5. Contract Description and Location:
Contract Price Including Approved Change Orders:
Contractor's Estimated Cost at Time of Bid (1):
Total Amount Billed to Date Including Retainage (2):
Total Costs To Date:
Total Revised Estimated Costs to Complete (3):
Estimated Completion Date:
 
6. Contract Description and Location:
Contract Price Including Approved Change Orders:
Contractor's Estimated Cost at Time of Bid (1):
Total Amount Billed to Date Including Retainage (2):
Total Costs To Date:
Total Revised Estimated Costs to Complete (3):
Estimated Completion Date:
 

CONTRACTS COMPLETED SINCE LAST FISCAL CLOSING STATEMENT OF LAST STATUS REPORT

1. Include contractor’s original estimated total cost plus cost of all change orders and extra work orders approved to date.

2. Do not include “claims” or “disputed items.” If desired, attach an explanation.

3. See instructions below.

For year and financial statements, please have this form filed by your auditor.

As your surety agent, we are as interested as you in accurate progress reports on our construction work. This form is intended to help present such a report.

As a guide, the following definitions are given so that the data presented will be more meaningful.

1. CONTRACT PRICE and CONTRACTOR’S ESTIMATED COST AT TIME OF BID should include approved change orders only and, in original estimated costs, the costs applicable thereto. Exclude claims and disputed items. If desired, an explanation of these items may be attached.

If contracts are on a unit price basis, and the estimated number of units approved has increased or decreased since bid date, adjust the original contract price and costs accordingly, using the original price and cost per unit as a base, and enter these amounts unless the change in unit quantity has contractually operated to change the unit price.

2. All projects should be listed: Bonded, non-bonded, lump sum and cost plus.

3. COSTS should be entered consistent with financial statement (Profit and Loss Report) allocation, excluding general and administrative (specifically unallocated) overhead.

4. BILLED TO DATE and COSTS TO DATE should be entered as of the same date or, when this schedule is provided in conjunction with a financial statement, consistent with their treatment in the financial report.

5. ESTIMATED COSTS TO COMPLETE should be a revised figure reflecting developments which have occurred subsequent to bid date causing a change in total cost (or cost per unit), if any, not merely a subtraction exercise. After approximately 50% completion, it is imperative that a re-evaluation of costs be made. In the early stages of a project, a re-evaluation of costs may be difficult and perhaps impractical.

 

 
1. Contract and Description:
Final Contract Price:
Total Cost:
Gross Profit or Loss:
 

2.

Contract and Description:
Final Contract Price:
Total Cost:
Gross Profit or Loss:
 

3.

Contract and Description:
Final Contract Price:
Total Cost:
Gross Profit or Loss:
 

4.

Contract and Description:
Final Contract Price:
Total Cost:
Gross Profit or Loss:
   
This information Prepared by: *
Date: *
   
   
top  

© 2003 Brokers' Risk Placement Service, Inc. All Rights Reserved

 
601 Oakmont Lane, Suite 400 • Westmont, IL 60559 • Phone 630.468.5600 • Toll Free 888.236.9514 • Fax 630.468.5697